Reserve at Green Valley Ranch senior community resident Lee Erickson address city council members Sept. 14, 2026 as other Reserve residents lock arms behind him. Erickson and other residents want city lawmakers to intervene in a proposed data center project near their community. SENTINEL SCREEN GRAB

EDITOR’S NOTE: This story has been corrected and clarified to show that the actual size of a proposed Trident data center project in Aurora is 860,000 square feet, not 1.5 million square feet. Also, the story now explains where the Trident project is in the approval pipeline process.

AURORA | Aurora lawmakers on Monday were divided on some restrictions on future data centers built in the city but unanimously agreed to limit the water-intensive use of evaporative-cooling at the controversial centers.

City lawmakers have struggled to agree on what some of the threats of the nationally and locally controversial computing centers could be to neighboring communities, but they agreed Monday the potentially millions of gallons of water large centers could use to cool computer components is a risk to the city’s water supply.

City officials approved a resolution on Aug. 10 directing the city manager to create new data center regulations within about a month, including a prohibition on evaporative cooling and a requirement for setbacks and landscape buffers for data centers in certain areas. 

Lawmakers on Monday voted 10-0 to prohibit data centers, or any industry, from using large-scale evaporative cooling in their design.

When it came, however, to regulating the distance between future data centers and nearby residential homes, the council was split.

Currently, city officials say there are five data centers operating in the city. Restrictions would only apply to other, currently un-approved projects. The QTS data center project near I-70 and E-470 is touted as the largest data center project in the state.

Another one of those unstarted projects could be targeted by the city’s developing legislation. While city lawmakers discussed potential residential set-backs in a study session Monday night, residents of Trident at Windler data center project, possibly involving a 860,000 square foot operation on 143 acres in northeast Aurora, flooded the later city council meeting to demand restrictions.

Residents of the Reserve at Green Valley Ranch senior living complex near the proposed site of the Trident project said they were never notified that the project was under consideration.

“For those of us living in a 55-plus community, which is literally just steps from the proposed site of the data center, quality of life matters,” resident Jacqueline Peterson told city council members. “I am especially concerned about the continuous noise from cooling equipment, air pollution, light pollution, contaminated water, diesel exhaust, and emissions from backup generators, increased demands on our water and electrical systems, reduction in property value, and long-term effects of placing a large industrial-type facility so close to an established residential community.”

City officials on Tuesday said a site plan and development application were filed with the city’s building department in August 2025.

“Those plans have been through two formal city reviews with a third underway now,” Aurora spokesperson Joe Rubino said in a statement. “Comments are due back to the applicant later this month. “

Rubino said the property is zoned for industrial and data centers are a permitted use, allowing the city to approved them administratively barring any requested major adjustments.

Last month, the council narrowly opposed a moratorium on new data centers while regulations are created and implemented. 

During the study session Monday night, the council was essentially split between progressive and conservative factions as to whether special setbacks should be imposed on future data centers, different from other industrial or commercial uses abutting residential communities.

Council members and staff slogged through trying to decide where setback perimeters would begin and end, measured from buildings, outside features, such as noisy generators, parking lots or other property lines. Lawmakers agreed to offer an arbitrary 350-feet setback temporarily and return to discuss future mandated setbacks at a future meeting.

As it stands, lawmakers agreed that setbacks be measured from the closest permanent building or critical equipment improvements, rather than parking areas, to the residential zone district. Dedicated public right-of-way and dedicated open space may count toward the setback distance.

Lawmakers disagreed on how the city should determine which data centers are subject to the most extreme future setbacks from residential areas based on data center size. Because of federal regulations, data centers do not have to make public exact usage of megawatts as a matter of anti-trust regulations. City officials are proposing a simple system of grading data centers as either those that use more than or less than 25 megawatts of electricity to operate.

Councilmember Curtis Gardner said that could be problematic because there is no direct correlation between building size and a data center operation and its above or below power usage.

City officials previously said there are five Aurora data centers in the development process and nine already established. Some regulations for data centers are already in place. 

Data centers are currently restricted in location to areas that are zoned industrial, airport districts or mixed-use office-industrial. Data centers can be built in certain mixed-use zoning restrictions under the conditional use process, which has additional requirements for public hearings and city council gets the ultimate decision. 

Water use for data centers is governed by the city’s large water user guide. For noise pollution, the city’s unified development code restricts the noise level at data centers to the same level as other businesses, with different allowances based on zoning and time.

City regulation of the centers comes as the nation grapples with controversy over federal regulations of Artificial Intelligence and the industry exploding around it. Many data centers support AI projects. But many data centers provide servers and other computer needs for applications as mundane as banking, streetlight operations or just data storage.

Join the Conversation

3 Comments

  1. This move was a start, but the moratorium should have been passed. All things tech try to move at a lightning pace, but in a dry climate special considerations must be made. Water usage is paramount, but other quality of life issues are very important. I see that president Trump has his foot on the gas for all things tech, but that only serves to tell me we should move with caution. He’s not exactly had a great track record, despite what he thinks!

  2. Mandate data centers use in ground, closed loop, geothermal cooling systems to cool their servers. Mandate a decibel level for operation which is acceptable to the neighbors and which, if exceeded will cause the loss of their certificate of occupancy. That puts the onus on the data center designers to address their nuisance effects rather than placing the burden on Council to figure out a laundry list of restrictions. Their walls will be thick, their utilities well shielded, and their setbacks will have to be large to accomodate the large fields for the cooling systems.

  3. Geo thermal is a great suggestion. Your thinking about the burden shift from community to the data centers is the way to move forward. Enough community capitulation to attract the promise of jobs that don’t materialize!