FILE - In this July 1, 2015 file photo, Veterans Affairs Deputy Secretary Sloan Gibson speaks near construction for the VA hospital during a news conference, in Aurora, Colo. A House committee will vote on whether to issue a subpoena to the Veterans Affairs Department demanding the agency turn over documents that could explain how the cost of a Denver-area VA hospital ballooned to almost $1.7 billion, nearly triple earlier estimates. The Veterans Affairs Committee scheduled a vote for Wednesday, Sept. 7, 2016, on a subpoena for documents gathered by a VA internal inquiry called an administrative investigation board. (AP Photo/David Zalubowski, File)

DENVER | Federal investigators say “gross mismanagement,” delays and lax oversight by the Department of Veterans Affairs added hundreds of millions of dollars to the cost of a new Aurora VA hospital and delayed it by years.

A report from the department’s internal watchdog released Wednesday also said a former senior VA official, Glenn Haggstrom, knew the project was veering toward huge cost overruns but didn’t tell lawmakers that when he testified before Congress in 2013 and 2014.

No phone number could be found for Haggstrom. He retired in 2015.

The report by the VA inspector general repeats some conclusions from earlier investigations but is the most scathing account of the project to date.

The hospital under construction in suburban Denver is expected to cost nearly $1.7 billion, nearly triple the 2014 estimate.